What OpenAI is built with: Stargate, cloud partners, chips and sub-processors
Three layers of OpenAI's stack
OpenAI's infrastructure has three layers, and each answers a different question. The compute layer covers the data centers and chips that train and run the models, which is where most of OpenAI's spending goes. The cloud layer covers the companies that operate that compute and host customer data, which matters for privacy and procurement. The web layer covers the public websites and apps, which the BuiltWith scan above reports. This guide covers the first two, using OpenAI's own announcements, its sub-processor list and reporting from CNBC, The Information and Data Center Dynamics.
| Layer | Main providers | Where to check |
|---|---|---|
| Data centers | Oracle, SoftBank, CoreWeave, Microsoft, AWS, Crusoe, Vantage | OpenAI's Stargate announcements |
| Chips | Nvidia, AMD, Broadcom (custom), Cerebras | OpenAI and partner press releases |
| Customer data hosting | Azure, AWS, Google Cloud, Oracle, CoreWeave, Cerebras | OpenAI sub-processor list |
| Delivery and support | Cloudflare, Snowflake, TaskUs and others | OpenAI sub-processor list |
Stargate and the data centers
OpenAI announced Stargate at the White House on January 21, 2025, with Oracle and SoftBank as lead partners, promising $500 billion and 10 gigawatts of US AI infrastructure. A gigawatt is roughly the output of a large power plant, and at current chip density it powers several hundred thousand AI accelerators.
The flagship campus is in Abilene, Texas, built by Crusoe and run on Oracle Cloud Infrastructure. Oracle began delivering Nvidia GB200 racks in June 2025, and OpenAI says GPT-5.5 was trained there. In July 2025 OpenAI and Oracle agreed to develop 4.5 more gigawatts, a partnership OpenAI valued at over $300 billion across five years. September 2025 added five sites: Shackelford County, Texas, Doña Ana County, New Mexico and a Midwest site later named as Port Washington, Wisconsin, developed by Oracle and Vantage, plus two SoftBank sites in Lordstown, Ohio and Milam County, Texas.
By April 29, 2026, OpenAI said it had passed the 10 gigawatt goal, with more than 3 gigawatts added in the previous 90 days. Contracted capacity differs from running capacity. OpenAI said its compute more than tripled during 2025 to about 1.9 gigawatts, and most Stargate sites deliver in stages through 2027 and 2028.
The plan has changed along the way. The Information reported in March 2026 that OpenAI dropped its aim of owning data centers, because lenders charged much less when Oracle or another creditworthy partner signed the lease. OpenAI also chose not to expand the Abilene campus further and to put that capacity elsewhere. Reported compute commitments through 2030 fell to around $600 billion, from earlier talk of $1.4 trillion.
The cloud partners
Microsoft was OpenAI's only cloud provider from 2019 to early 2025 and remains a major investor. The companies changed their deal in January 2025 so OpenAI could buy capacity from others, with Microsoft holding a right of first refusal, and restructured again when OpenAI became a public benefit corporation in October 2025. Azure still hosts much of the API.
The other clouds followed:
| Provider | Deal | Role |
|---|---|---|
| Oracle | Over $300 billion across five years, July 2025 | Stargate sites, API and ChatGPT hosting |
| Amazon Web Services | $38 billion, November 2025 | Nvidia capacity in AWS data centers, plus new builds |
| Google Cloud | Finalized 2025 | Additional capacity, GPUs rather than TPUs |
| CoreWeave | Multiple contracts since 2025 | GPU cloud for training and inference |
| Cerebras | Over $10 billion, January 2026 | 750 MW of fast inference through 2028 |
OpenAI said in June 2025 that it had no plans to use Google's TPU chips at scale, so its Google Cloud capacity runs on Nvidia GPUs.
The chips
Nvidia supplies most of OpenAI's compute today, through GB200 systems at Abilene and capacity rented from Azure, Oracle, AWS and CoreWeave. In September 2025 the companies signed a letter of intent for at least 10 gigawatts of Nvidia systems, with the first gigawatt on the Vera Rubin platform in the second half of 2026. Tom's Hardware reported in February 2026 that Nvidia was moving toward a direct equity stake of about $30 billion as part of OpenAI's funding round, in place of the original milestone-based plan.
AMD signed a 6 gigawatt agreement on October 6, 2025. The first gigawatt of Instinct MI450 GPUs starts in the second half of 2026, and AMD gave OpenAI a warrant for up to 160 million AMD shares that vests as deployments and share-price targets are met.
Broadcom is building OpenAI's own chip. The companies announced on October 13, 2025 a plan for 10 gigawatts of OpenAI-designed accelerators, with racks connected by Broadcom Ethernet, starting in the second half of 2026 and finishing by the end of 2029. Broadcom's chief executive told investors in December 2025 that he expected little revenue from the project in 2026.
Cerebras builds wafer-scale chips that run models much faster than GPUs for some tasks. OpenAI's January 2026 deal covers 750 megawatts across tranches through 2028, aimed at low-latency inference.
Sub-processors for customer data
For anyone reviewing OpenAI as a vendor, the sub-processor list matters more than the chip deals. It names the companies that handle customer data for the API, ChatGPT Enterprise, Edu and Business. The table above this guide summarizes it. Cloud hosts are spread across many countries, from Finland, Japan, Norway and the UK on Google Cloud to Brazil, Malaysia and the Netherlands on Oracle, and Norway, Spain and Sweden on CoreWeave. Cloudflare serves content from edge locations near users. Snowflake stores analytics data in the US. TaskUs handles some support work from the Philippines.
OpenAI offers data residency for eligible business and API customers in several regions, including Europe, the UK, Japan, India and others, which keeps stored data in that region. Check the current list and residency page before signing, since both change.
What this means for users
For most ChatGPT users, the infrastructure is invisible, but it explains a few things. Capacity limits during launches, such as the image generation rush in March 2025, come from compute shortages that these deals are meant to fix. Faster responses on some models trace to Cerebras and newer Nvidia hardware. And because OpenAI relies on several clouds, an outage at one provider usually affects only some services.
For businesses, the multi-cloud setup means your data may be processed by more than one hosting company. Read the sub-processor list, ask about data residency, and confirm which regions apply to the products you buy.
Related: what Anthropic is built with, what Google Gemini is built with, ChatGPT review.
Frequently asked questions
What cloud does OpenAI use?
OpenAI uses several. Its sub-processor list names Microsoft Azure, Oracle Cloud Infrastructure, Amazon Web Services, Google Cloud Platform, CoreWeave and Cerebras as hosts for the API and business ChatGPT products, with regions that vary by provider. Microsoft was OpenAI's exclusive cloud until early 2025, when the companies changed their agreement so OpenAI could buy capacity elsewhere. Microsoft still provides cloud services through Stargate.
What is Stargate?
Stargate is OpenAI's program for building AI data centers, announced at the White House in January 2025 with Oracle and SoftBank and a target of $500 billion and 10 gigawatts in the United States. The flagship site in Abilene, Texas runs on Oracle Cloud with Nvidia GB200 racks. Other sites include Shackelford County, Texas, Doña Ana County, New Mexico, Port Washington, Wisconsin, Lordstown, Ohio and Milam County, Texas. OpenAI said in April 2026 that it had passed the 10 gigawatt goal. Reporting in March 2026 said OpenAI had dropped plans to own data centers and would lease capacity through partners instead.
What chips does OpenAI use?
Mostly Nvidia GPUs, including GB200 systems at Abilene, with Nvidia's Vera Rubin platform planned for the second half of 2026. OpenAI also has a 6 gigawatt agreement with AMD starting with Instinct MI450 GPUs in the second half of 2026, a 10 gigawatt plan with Broadcom for OpenAI-designed custom accelerators through 2029, and 750 megawatts of Cerebras wafer-scale systems for low-latency inference through 2028.
Does OpenAI own its data centers?
No. OpenAI leases capacity. Oracle, SoftBank, CoreWeave, Microsoft, Amazon and others build or operate the data centers, and OpenAI signs long-term contracts for the compute. The Information reported in March 2026 that lenders offered better terms when a partner with a stronger credit rating, such as Oracle, signed the lease, which led OpenAI to drop plans to own facilities directly.
Who processes my data when I use ChatGPT Enterprise or the API?
OpenAI's sub-processor list covers the API, ChatGPT Enterprise, Edu and Business. It names cloud hosts such as Azure, AWS, Google Cloud, Oracle, CoreWeave and Cerebras, Cloudflare for content delivery, Snowflake for data warehousing and TaskUs for customer support in the Philippines, among others. The list changes, and OpenAI publishes updates on the page linked from this profile, so check it during any vendor review.